October 25, 2024- Patrick Henry Court Drainage Improvement Project UPDATE

  • Contractor received Land Disturbance Permit. 
  • Contractor has begun excavating project areas in Hollyfield Park and installed erosion and sediment controls at the project sites.
  • Contractor (Steady Construction) has completed 63% of test pits along the pipe routing. Each test pit will remain unfilled until the new drainage is installed. 
  • Site Safety fencing has been installed in the Hollyfield Park. 
  • Hollyfield Park playground is closed and will remain closed until the project is completed.
  • Pickleball/Tennis courts will remain open.