11/8/2024
Progress Update: Patrick Henry Court Drainage Improvement Project
• Contractor (Steady Construction) has completed all test pits. Each test pit will remain unfilled until the new drainage is installed
• Excavation of the detention water basin will continue at Hollyfield Park through Nov.15.
• A new Hollyfield parking area is open and accessible by members. The parking area near the baseball field at the back of Hollyfield Park has been closed to members until further notice.
• Tree removal in the back area of Hollyfield Park will begin the week of Nov.18.
• Hollyfield Park playground is closed and will remain closed until the project is completed.
• Pickleball courts and Tennis courts remain open.