Progress Update Friday, March 19, 2025:
Utility Conflict: Steady Construction has discovered a 12-inch water main conflict at the planned manhole structure on Yorktown Boulevard.
- RSA will resolve the issue, with work expected to be completed within 2-3 weeks after the bidding process.
- This must be addressed before drainage pipeline work crossing Yorktown Blvd. can proceed
Road Closures:
- Yorktown Boulevard (from Patrick Henry Court to Fairfax Lane) will remain closed until further notice.
- Patrick Henry Court Intersection Closure: Delayed by approximately 7 days due to rock encounters during pipeline work on Yorktown Blvd. Members will be notified prior to the closure.
Construction Update:
- Drainage Pipeline installation on Patrick Henry Court is progressing, crews working from Hollyfield Park toward the intersection at Yorktown Boulevard.
- Crews encountered rock while installing the pipeline along Yorktown Boulevard roadside, slowing progress in this area.
Hollyfield Park Water Detention Basin:
Work is ongoing but has been delayed a few days due to rock obstructions.
Reopening of Facilities:
- The back parking lot near the ball field and pickleball courts will reopen by Friday, March 28.
- The ball field will also be available for use after March 28.
- The pickleball and tennis courts remain open.
Hollyfield Park playground is closed and will remain closed until the project is completed.
ROAD CLOSURE REMINDER:
Yorktown Blvd. will be closed to thru traffic from the intersection of Patrick Henry Court and Fairfax Lane until further notice.
Only local traffic will be allowed to access this section of Yorktown Blvd.
Please use alternate routes avoiding this area of Yorktown Blvd if possible during the scheduled Road Closure.