UPDATE January 14, 2025

1/14/2025

Patrick Henry Court Drainage Improvement Project Update 1/14:
  • Tree removal will proceed along the pipeline on Patrick Henry Ct and Yorktown Blvd the week of 1/14 through 1/21. LOWA E&S has marked the property lines in this area with green ribbons on stakes. Any trees between the road and the green stake (Utility Easement) that prohibit excavation will be removed.
  • Tree cutting is complete at the the two LOWA Lots (707 & 709 Yorktown Blvd) for the stormwater basin location, removal of these trees from the lots will begin 1/15. Please be aware that traffic on Yorktown Blvd in the 700 block area could be interrupted during the tree removal process.
  • Pipeline construction will begin in the next 7 days (weather permitting) on Patrick Henry Court and the 700 block area of Yorktown Blvd. This construction could cause traffic interruptions. Please avoid driving through these areas, when possible, to avoid unnecessary delays or congestion in these construction zones.
  • The drainage connection between Hollyfield and Patrick Henry Court is currently being constructed.
  • The parking area near the baseball field at the back of Hollyfield Park has been closed to members until further notice.
  • Hollyfield Park playground is closed and will remain closed until the project is completed.
  • Pickleball courts and Tennis courts remain open, weather permitting.