December 11 Progress Update:
Hollyfield Park Work:
  • The horseshoe pit has been marked out and installation by the contractor (Steady Construction) is in progress and is expected to be completed before the end of the month.
  • Tree replacement has been marked out by LOWA and will be installed after final grade of the project area. Two shade trees in the parking area have been planted.
Patrick Henry Court Pipeline Work:
  • RSA has completed all utility conflict work on Patrick Henry Court.
  • Steady Construction began ditch and manhole structure work at the intersection of Patrick Henry Court and Yorktown Blvd. the week of December 9 and was scheduled to complete work by Friday, December 12, weather permitting.  
  • Steady Construction has two more drainage pipeline crossings to complete on Patrick Henry Court. When contractor crews work on drainage pipelines that cross Patrick Henry Court, they will cut into the roadway halfway across, allowing one lane of traffic to remain open in the active work zones. Once each pipeline section is installed, the roadway will be backfilled and reopened to full traffic.
Yorktown Blvd. Water Detention Facility Work:
  • A gravel entrance area, vegetated spillway, and a removable bollard at the driveway remain to be finished.
Final Steps:
Once all pipeline crossovers on Patrick Henry Court are completed:
  • Crews will complete final site cleanup and demobilization of construction equipment.
  • Paving on Yorktown Blvd. and tar-and-chip work on Patrick Henry Court will be completed in the Spring for optimal weather conditions.
  • Tar and chip will be applied to all Hollyfield Park parking areas after construction in the Spring for optimal weather conditions.
  • Erosion and sediment control fencing will remain in place until new grass is fully established.