Progress Update April 8, 2025:
Utility Conflict: LOWA is waiting on RSA to provide bids to resolve the utility conflict issue, work expected to be completed within 2-3 weeks after the bidding process is complete.
- This conflict must be resolved before the drainage pipeline work crossing Yorktown Blvd. can proceed.
Road Closures:
- Yorktown Boulevard (from Patrick Henry Court to Fairfax Lane) will remain closed until further notice.
- Patrick Henry Court/Yorktown Blvd. Intersection: Closure has been delayed due to rock encounter in the drainage pipe area on either sides of the intersection of Patrick Henry Court and Yorktown Blvd. The Contractor will use a metal plate over the pipeline construction area in the road to allow local traffic to access Patrick Henry Court. Estimated time of road crossover work during the week of 4/14.
Construction Update:
- Crews are working on the drainage pipeline from Hollyfield Park water detention basin moving toward the connection at Patrick Henry Court. Progress is delayed due to bed rock encounters.
- Construction of the pipeline along the roadside of Yorktown Boulevard is underway and has reached the intersection of Patrick Henry Court and Yorktown Blvd.
- Two manhole structures are being installed the week of 4/8 on either sides of Patrick Henry Court/Yorktown Blvd intersection.
- The week of 4/14 pipeline work will continue up Patrick Henry Court toward Hollyfield Park pipeline connection.
- The back parking lot near the ball field and pickleball courts has reopened.
- The ball field at Hollyfield Park is open for use.
Hollyfield Park playground is closed and will remain closed until the project is completed.
ROAD CLOSURE REMINDER:
Yorktown Blvd. is closed to thru traffic
from the intersection of
Patrick Henry Court and Fairfax Lane
until further notice.
Only local traffic will be allowed to access this section of
Yorktown Blvd.
Please use alternate routes avoiding this area of Yorktown Blvd