10/18/2024
UPDATE October 18, 2024 Main Gate Project:
- Hosted a member info session with LOWA Staff and contractor (BZ Excavating, Inc.) at the Holcomb building about Main Gate project details and timelines from 5PM - 6PM on Thursday, October 17.
- Contractor (BZ Excavating, Inc) will begin staking out project zones and site prepping the week of 10/23.
- VDOT site comments received. Project Engineers have addressed comments. LOWA is waiting on VDOT and Orange County approvals of site plans for permitting.
- Street light fixtures and poles have been received.
- Median work for light pole installation and ground excavation in relocated member lane area will begin once permitting is received.