UPDATE November 22, 2024

11/22/2024

Progress Update 11/22/24:
  • Pausing site work during the Thanksgiving holiday week to alleviate congestion at the Main Gate area.
  • Work will resume the first week of December.
  • Contractor (BZ Excavating) has excavated the area of the relocated member lane on the far-right side of project zone.
  • A third-party inspection of the first sequence of excavation work has been done and we are waiting for geotechnical site inspection results.