UPDATE November 15, 2024

11/15/2024

Progress Update: Main Gate Traffic Congestion Relief Project:
  • Work will continue on site prep for new electrical for light fixtures in the main gate area. No Member Lane closures expected in the next sequence of site prep for electrical wiring.
  • Contractor (BZ Excavating) has excavated the area of the new relocated member lane on the far-right side of project zone.  
  • A third-party inspection of the first sequence of excavation work has been done and we are waiting for inspection sample results.