UPDATE November 12, 2024:
- Contractor (BZ Excavating) has excavated the area of the new relocated member lane on the far-right side of project zone.
- Main Gate work schedule change: Work will include site prep for new electrical for light fixtures in the main gate area which will begin in the next 7 days.
- No Member Lane closures expected in the next sequence of site prep for electrical wiring.
- A third-party inspection of the first sequence of excavation work is being scheduled.