Progress Update: Main Gate Traffic Congestion Relief Project:
  • LOWA received approvals of site plans for permitting from Orange County and VDOT.
  • Contractor (BZ Excavating) has received all permitting to proceed with the Main Gate project.
  • Site prepping will begin early next week (11/4).
  • Median work for light pole installation and ground excavation in relocated member lane area will begin after site prepping is completed.