Progress Update: Main Gate Traffic Congestion Relief Project:  
  • Pausing site work during the Thanksgiving holiday week to alleviate congestion at the Main Gate area.
  • Contractor (BZ Excavating) has excavated the area of the relocated member lane on the far-right side of the project zone.
  • A third-party inspection of the first sequence of excavation work has been done and we are waiting for geotechnical site inspection results.