4/29/2025
Progress Update April 29, 2025:
Visitor Lane #1 will be closed
Tuesday, April 29 through May 2
Daily from 8AM-5PM (estimated).
Visitor traffic will be directed through the NEW VISITOR LANE #2 during working hours beside the new security kiosk.
Visitor Lane #1 will be reopened each evening for All Box access for overnight Visitor Traffic.
The Member Lane will remain open.
Contractor (BZ Excavating) will be constructing a sidewalk in the Main Gate median area that leads to the new Security Kiosk from the Security building.
- Concrete work was completed for the Security Kiosk Island April 23.
- Entrance lane remediation was completed Tuesday, April 22.
- Visitor Lane #2 swing gate was installed Thursday, April 24.
- The Security Kiosk was put into operation on Tuesday, April 29 while work was being done on the perimeter of the Security building beside the Visitor Lane.
- Prep work for milling and paving was completed Wednesday, April 23 for the U-turn lanes to be widened.
- A perimeter fence and Visitor Lane signage is scheduled to be installed the week of May 5.
- Milling and paving is scheduled for the Main Gate project beginning Sunday, May 11 through Thursday, May 15 during the overnight from 7 PM-7 AM to avoid Main Gate heavy traffic times.