UPDATE April 23, 2025

4/23/2025

Progress Update April 23, 2025:

  • Concrete work will be completed for the Security Kiosk Island Wednesday, April 23.
  • Entrance lane remediation was completed Tuesday, April 22. 
  • Visitor Lane #2 swing gate will be installed Thursday, April 24.
  • The Security Kiosk is projected to be operational by Friday, April 25.
  • The Visitor Lane #1 will close during working hours for the remainder of the Main Gate project after the Security Kiosk is operational.
  • Visitor traffic will be directed through the new visitor lane #2 during working hours beside the new security kiosk. All Box access located in Visitor Lane #1 will be available for overnight Visitor Traffic.
  • Work will begin in the U-turn medians Wednesday, April 23 to widen the U-turn lanes. Only one U-Turn will be closed at a time during this work.
  • The Member Lane will remain open.