11/5/2024
LOWA Lakeview Parkway Paving Project Update 11/5:
- Milling on Lakeview Parkway from the intersection of the 100 block of Stratford Circle to Taylor Court has been completed. (Area 1)
- Milling the second area of Lakeview Parkway-Spotswood Road to Lake of the Woods Way has been completed.
- There will be signage for rough road areas and flaggers for lane transitions.
- The contractor will begin paving Area 1 beginning Wednesday, Nov.6 as that area is completed they will move to Area 2.
- Paving will occur from Nov. 6-13.
LOWA Lakeview Parkway Paving Project Update 11/1:
- Milling on Lakeview Parkway from the intersection of the 100 block of Stratford Circle to Taylor Court has been completed. (Area 1)
- The Contractor will mill the second area of Lakeview Parkway-Spotswood Road to Lake of the Woods Way beginning Monday, Nov.4 (Area 2)
- All milling should be completed by Nov.7.
- There will be signage for rough road areas and flaggers for lane transitions.
- The contractor will pave area 1 beginning Monday, Nov.4.
- Paving will occur from Nov. 4-11.
Please proceed in these areas of Lakeview Parkway with caution.
- Be cautious when traveling through the Lakeview paving zones.
- Keep an eye out for workers on the shoulders and moving around the paving areas.
- Keep an eye out for new traffic patterns or flaggers on Lakeview
- There WILL be potential traffic delays or temporary lane closures for short periods of time.