11/1/2024
Progress Update: Patrick Henry Court Drainage Improvement Project
- Contractor (Steady Construction) has received all permits for the project.
- Site Safety fencing has been installed in Hollyfield Park.
- Excavating has begun in the project zones of Hollyfield Park.
- 63% of test pits have been completed along the pipe routing. Each test pit will remain unfilled until the new drainage is installed.
- Hollyfield Park playground is closed and will remain closed until the project is completed.
- Pickleball courts and Tennis courts remain open.