1/8/2025
Progress Update: Patrick Henry Court Drainage Improvement Project:
- Tree removal will proceed along the pipeline on Patrick Henry Ct, Yorktown, and the two LOWA Lots (707 & 709 Yorktown Blvd) the week of 1/6, weather permitting. LOWA E&S has marked the property lines in this area with green ribbons on stakes. Any trees between the road and the green stake (Utility Easement) that prohibit excavation will be removed.
- Rock has been encountered in multiple locations of the project areas in excess of what had been originally estimated for the project. The engineering firm (AMT) is working on revised plans to remediate those obstacles in the project.
- Utility hole structures and piping have been installed from Flat Run Road to the detention facility in Hollyfield park.
- The drainage connection between Hollyfield Park and Patrick Henry Court is currently being constructed.
Pickleball/Tennis courts remain open, weather permitting.
Hollyfield Park playground is closed and will remain closed
until the project is completed.
Contractor (Steady Construction) works business days and weekends
depending on work
and weather 7:30 AM-5:00 PM (estimated).
Projected completion by March of 2025.