Skip to content
Member Login
Logout
Home
Latest News
Life at the Lake
Play & Explore
Events & Connections
The Heart of Lake Life
Events & Meetings
About
Local Info
Local Links
Clubs
Community Organization & Resources
Latest News
Dam Emergency Action Plans
Employment Opportunities
LOWA Amenity Map
Administration
Board of Directors
Forms
Governing Documents
Requests for Proposals
Golf
Subscribe to Golf Email
Amenities
Restaurants
Clubhouse
Fareways Cafe
Community Center
Equestrian Center
Fitness Center
LOWA Communications
Lakes & Marinas
Pickleball & Tennis
Swimming Pools
SOGGY DOGGIE
Parks and Campground
Boat Test & Registration
Calendar & Events
LOWA FALL FESTIVAL
LOWA Independence Day Celebration
LOWA Parade Recognitions
Holiday Home Decorating Contest
Holiday Home Decorating Contest WInners
Security
TEK Control LOG-IN
Contact Us
Contact Our Team
Smart Web
Real Estate
Page content
UPDATE January 8, 2025
1/8/2025
Progress Update: Main Gate Traffic Congestion Relief Project:
The remediation plan for substrate findings was rescheduled to occur this week, inclement weather has delayed that work.
Findings of the Inspection of geotechnical subgrade of the relocated Member Lane: The subgrade was found to be insufficient for a roadway base in one area of the project which requires remediation by the Contractor. Testing showed substrate was clay in one of the locations and needs an undercut based on VDOT requirements.
The Secondary Guard Building has been completed in fabrication and is ready to ship to the site when the base platform is completed.
Contractor (BZ Excavating) works business days depending on work
and weather 7:30 AM-5:00 PM (estimated).
Projected completion by March of 2025.