Skip to content
Member Login
Logout
Home
Latest News
Life at the Lake
Play & Explore
Events & Connections
The Heart of Lake Life
Events & Meetings
About
Local Info
Local Links
Clubs
Community Organization & Resources
Latest News
Dam Emergency Action Plans
Employment Opportunities
LOWA Amenity Map
Administration
Board of Directors
Forms
Governing Documents
Requests for Proposals
Golf
Subscribe to Golf Email
Amenities
Restaurants
Clubhouse
Fareways Cafe
Community Center
Equestrian Center
Fitness Center
LOWA Communications
Lakes & Marinas
Pickleball & Tennis
Swimming Pools
SOGGY DOGGIE
Parks and Campground
Boat Test & Registration
Calendar & Events
LOWA FALL FESTIVAL
LOWA Independence Day Celebration
LOWA Parade Recognitions
Holiday Home Decorating Contest
Holiday Home Decorating Contest WInners
Security
TEK Control LOG-IN
Contact Us
Contact Our Team
Smart Web
Real Estate
Page content
UPDATE February 7, 2025
2/5/2025
Progress Update: Main Gate Traffic Congestion Relief Project:
The Contractor (BZ Excavating) completed the remediation plan for subsurface findings on 1/30 for the relocated member lane.
Winter weather on 2/5 and 2/6 delayed the main gate project schedule during the week of 2/3.
BZ Excavating requires at least two consecutive days of clear weather to dry out and compact the roadway surface before the asphalt contractor can apply the base coat.
LOWA is using a geotechnical engineer to confirm the proper compaction for the relocated member lane before the asphalt basecoat work is done.
Boring for electrical wiring of relocated member lane island and guard shack will be scheduled to begin in the next two weeks, weather permitting. Start date contingent on receipt of final wiring plan from Entry Guard (vendor) to the contractor (BZ Excavating).