Clubhouse Area Recreation Complex Project


The Clubhouse Area Recreation Complex Project (CARC) is a major capital project that is designed to reconstruct, renovate, update the amenities in the area of the Clubhouse. The CARC project gives our community 25 ADA-compliant parking spaces for the Clubhouse, beach, fitness center and pool. Our old beach bathrooms will be replaced and moved closer to the beach. The fifty-year old bathhouse/fitness center building will be replaced with new infrastructure that will better meet the needs of our members. The swimming pool will be replaced with a/multipurpose pool that will meet the needs of all ages, from toddlers to seniors, as well as the needs of our physically challenged members. The old snack bar for the pool will be replaced by a new snack bar serving all members using the Clubhouse beach area, not just pool users. A new basketball court will be built for our youth to replace the old court.

Clubhouse Area Recreation Complex

Project Update: As of March 28, 2018

Project Cost Estimate:  $5.14 Million ($5,135,324)

RRMM Lukmire Architects Cost Comparison
Downey Scott Cost Estimate- February 22, 2018

 Current Funding:        
  • $458,422 – Cash on hand
  • $818,000 – Year 1 ($191/lot) to be billed in Regular Assessment
  • $5 Million bank loan application submitted/pending approval
 Project Progress
Design: 100 percent complete
Permitting: State & County permitting in progress
  • Virginia DEQ review complete
  • Site Plan permit pending with comments received from Orange County, RSA, and Soil & Water Conservation District
  • Building permit approved March 9, 2018
Bidding: Preparing for competitive bidding April 2, with bids due April 27, for award May 5 or 16
  • Bid documents complete
  • Four general contractors identified for direct contact
  • Project announcement to other general contractors via Blue Book Building & Construction Network
  • RFP for LOWA Clerk of the Works position released March 6, due April 5.
Construction: Schedule May 2018-May 2019
  • Clubhouse Pool closed for Summer 2018
  • Planning for temporary Fitness Center move in May to the Clubhouse Lower Level
Communication:
  • GM planning Open House information session for April 30.
 Join us at the Information Session & Tour of Proposed Project Site on Monday, April 30, from 6-8 PM, in the Clubhouse.

Project Information Links

Click on the links below for more information about the project:

CARC NEWSFEED

Lake Currents Articles Regarding CARC

CARC Project Management Timeline